PSP Projects Limited Q1 FY25 Earnings Conference Call Summary
Date and Submission • Date of Call: August 2, 2024 • Submission to BSE and NSE: August 8, 2024
Key Financial Highlights • Order Book: Rs. 5,890 crore (11% YoY growth) • Quarterly Revenue: Rs. 612 crore (20% YoY increase) • EBITDA: Rs. 73 crore (14% growth, 12% margin) • Net Profit: Rs. 34 crore (7% YoY decline)
Project Updates • Progress: Ongoing projects facing labor and weather challenges, expected ramp-up in Q2 FY25. • EBITDA Margin Discussion: Lower than expected due to increased costs and delays, particularly in UP Medical projects.
Financial Projections and Targets • Revenue Target for FY25: Rs. 2,800 crore (15% growth) • Bid Pipeline: Rs. 6,400 crore • Debt Reduction: From Rs. 455 crore in March to Rs. 200 crore in June.
Outstanding Payments and Debt Management • Surat Diamond Bourse: Expected to receive Rs. 225 crore, with Rs. 104 crore already received. • Debt Repayment: Gross debt reduced to Rs. 200 crore after repayments.
Challenges and Outlook • UP Project: Anticipated additional pressure on EBITDA due to rising costs. • EBITDA Margin Stabilization: Expected around 10-11%, down from historical levels.
Capital Expenditure and Financial Management • Capex: Q1 spend of Rs. 17 crore, projected annual capex of Rs. 60 crore. • Finance Costs: Slight reduction expected moving forward.
Future Prospects • Revenue from Surat Project: Projected Rs. 350-400 crore. • Order Inflow Target: Rs. 3.5 billion for the year, with year-to-date inflow at Rs. 230 crore. • Semiconductor Industry Participation: Inquiry about involvement in Gujarat's emerging sector.
Conclusion • Future Orders: Anticipation of securing significant orders valued between Rs. 800-1,000 crore. • Labor Issues: Temporary reduction in labor at SMC project, but on track without penalties. • Precast Facility: Operating at 50-60% capacity, plans for expansion once utilization increases.
Closing Remarks • Gratitude: Thanks to participants and invitation for further inquiries through investor relations.
PSP Projects Limited Q4 FY24 Earnings Conference Call Summary
Company Overview • Date of Call: May 24, 2024 • Submission to BSE and NSE: Transcript submitted on May 30, 2024 • Key Management: Chairman and CEO P.S. Patel, CFO Hetal Patel
Financial Performance Highlights • Record Order Book: INR 6,049 crore (20% YoY increase) • Order Inflow: INR 3,498 crore • Projects Completed: 17 projects; awarded 27 new projects • FY24 Revenue: INR 2,462 crore (28% growth) • EBITDA Margin: 10.62% • FY25 Order Inflow Projection: INR 3,500 crore
Q4 FY24 Financial Results • Revenue: Decreased by 11% to INR 649 crore • EBITDA: Fell by 33% to INR 52 crore • Net Profit: Dropped by 67% to INR 15 crore • EBITDA Margin: Decreased to 7.98% from 10.67% • FY24 Net Profit: Decreased by 7% to INR 124 crore
Capital Expenditure and Debt • Total Capex: INR 150 crore (investments in precast facilities) • Long-term Borrowings: INR 95 crore • Short-term Borrowings: INR 360 crore
Future Outlook • Revenue Growth Projection: Minimum of 15% for FY25 • Expected Cash Inflow: INR 100 crore within a month • Pending Receivables: INR 200 crore from Surat Diamond Bourse, INR 80 crore from UP medical colleges
Project Updates • Uttar Pradesh Projects: INR 741 crore booked in FY24 • Precast Facility: Gross block of INR 200 crore; expected revenue growth to INR 350-400 crore annually • SMC Surat Project: Revenue of INR 160-170 crore booked; expected completion within FY25
Margin Guidance • Target Margin for FY25: 10%-11% • Challenges: Increased overhead and labor costs affecting margins
Additional Insights • Arbitration Cases: Updates on Bhiwandi and Pandharpur cases • Concerns Addressed: Lower revenue growth and EBITDA margins; need for robust order inflow emphasized
Conclusion • Overall Guidance: 15% sales growth for FY25, with a focus on improving margins and addressing project-specific challenges.
PSP Projects Limited Q3 FY24 Earnings Conference Call Summary
Date and Submission • Date of Call: February 9, 2024 • Submission to BSE and NSE: February 16, 2024
Key Participants • Chairman and CEO: P.S. Patel • CFO: Hetal Patel • Moderator: Shravan Shah (Dolat Capital)
Project Highlights • Completed Projects: Seven, including: • Residential project for Adani Realty • Industrial warehousing projects in Gujarat • New Projects Awarded: Two, including Kalamkhush Campus at Gandhi Ashram • Order Inflow: Rs. 1,060 crore • Outstanding Order Book: Rs. 4,443 crore (12% year-on-year decline)
Financial Overview • Revenue from Operations: Rs. 697 crore (40% YoY increase) • EBITDA: Rs. 71 crore (16% increase) • Net Profit: Rs. 33 crore (8% decrease) • PAT Margin: Declined from 7.01% to 4.63% • Cumulative Revenue (9 months): Rs. 1,433 crore • CAPEX: Rs. 142 crore for precast facilities • Total Borrowings: Rs. 478 crore
Strategic Focus • Shift Towards Larger Projects: Emphasis on infrastructure development • Projected Full-Year Revenue for FY24: Rs. 2,500 - Rs. 2,600 crore • Target for FY25: Rs. 3,000 crore • Margin Estimate: Conservative at 11-12%
Legal and Financial Matters • Ongoing Legal Issues: Claims from Surat Diamond Bourse affecting cash flow • Pending Payments: Rs. 141 crore from UP projects • Unbilled Revenue: Rs. 409 crore • Debt Management: No plans to increase debt; focus on equity raising for growth capital
Future Projects and Bids • Current Bid Pipeline: Rs. 6,000 crore (excluding cancelled Delhi railway station project) • Upcoming Projects: Gatishakti project (Rs. 630 crore), Dharoi and Sabarmati Riverfront projects (over Rs. 400 crore) • Lulu Mall Project Bid Size: Estimated between Rs. 500 crore to Rs. 1,000 crore
Precast Operations • Expected Revenue: Over Rs. 180 crore by year-end • Current Capacity Utilization: 40-50% of 30 lakh square feet per year • Future CAPEX for Precast: Over Rs. 100 crore anticipated
Conclusion • Management's Outlook: Optimistic about recovering outstanding amounts and maintaining margins • Gratitude Expressed: Thanks to participants for their support and trust
PSP Projects Limited Q2 FY24 Earnings Conference Call Summary
Date and Submission • Date of Call: November 2, 2023 • Submission to BSE and NSE: November 8, 2023
Key Highlights • Project Awards: • 9 projects awarded in Q2 FY24 • 14 projects awarded in H1 FY24 • Notable projects include a commercial building in Gift City and a chocolate plant expansion • Project Completion: • 2 projects completed in the quarter • Outstanding order book: Rs. 4,898 crore (4% decline YoY)
Financial Performance • Revenue Growth: • Revenue increased by 70% to Rs. 607 crore • EBITDA rose by 91% to Rs. 74 crore • Net profit increased by 71% to Rs. 39 crore • Margins: • EBITDA margin: 12.2% • PAT margin: 6.4% • Order Inflow: • Q2 order inflow: Rs. 175 crore • H1 total order inflow: Rs. 934 crore • FY24 target: Rs. 3,000 crore
Balance Sheet Highlights • Current Borrowings: • Increased from Rs. 107 crore to Rs. 377 crore • Bank Credit Facilities: • Expanded from Rs. 1,047 crore to Rs. 1,497 crore • Work on Hand: • Total work on hand: Rs. 4,898 crore • Bid pipeline: Rs. 6,500 crore
Management Guidance • Future Performance: • Revenue and margin guidance maintained • Emphasis on project execution for future performance
Key Discussions • Credit Facilities: • Total credit facility limit: Rs. 1,497 crore • Current utilization: Rs. 210 crore (fund-based), Rs. 725 crore (non-fund based) • Bid Pipeline: • Total bid pipeline exceeds Rs. 10,000 crore • Significant project: Delhi Railway Redevelopment • Precast Facility: • Total investment: Rs. 160-165 crore • Production capacity increased from 1 million to 3 million square feet
Concerns and Projections • Debt Levels: • Gross debt expected to remain above Rs. 300 crore • Revenue Growth: • Projected sustainable revenue growth of 20%-25% for FY25-26 • Cash Balance: • Current cash balance: Rs. 285 crore
Additional Insights • Impact of Elections: • No anticipated slowdown in bids due to elections • Ongoing Projects: • AIIMS project in Rewari, Haryana, and a new university project in Lucknow valued at Rs. 525 crore • Future Expectations: • Improvement in cash flow expected by end of FY24 • Total revenue projection for the year: Rs. 2,600 crore
Conclusion • Management expressed optimism about diversifying the order book and maintaining profit margins despite competitive pressures. The call concluded with well wishes for the upcoming Diwali festival.
PSP Projects Limited Q1 FY24 Earnings Conference Call Summary
Date and Submission • Date of Call: July 27, 2023 • Submission to BSE and NSE: August 2, 2023
Key Financial Highlights • Revenue from Operations: Increased by 48% to Rs. 510 crore • EBITDA: Rose by 37% to Rs. 65 crore (EBITDA margin: 12.7%) • Net Profit: Grew by 29% to Rs. 37 crore (PAT margin: 7.13%) • Outstanding Order Book: 15% year-over-year growth, totaling Rs. 5,321 crore • New Orders: Received Rs. 758 crore, a 38% increase in order inflow year-over-year
Operational Updates • Projects Completed: Five projects during the quarter • Revenue from UP Projects: Rs. 196 crore, cumulative revenue of Rs. 915 crore • Borrowings: Long-term borrowings of Rs. 97 crore; short-term borrowings of Rs. 185 crore • Credit Facility Utilization: Rs. 905 crore out of Rs. 1,047 crore
Future Outlook • Revenue Guidance: Maintained at Rs. 2,600 crore for the year • Bid Pipeline: Approximately Rs. 6,000 crore, including upcoming bids for Ahmedabad and Delhi railway stations • Infrastructure Investment: Positive outlook due to Gujarat government's plans
Management Insights • Precast Operations: Target revenue of Rs. 250 crore for the year, potential growth to Rs. 1,000 crore • Debt Management: Increase in debt due to inventory investments, projected reduction by year-end • Joint Ventures: Pursuing partnerships for large railway and airport projects
Q&A Highlights • Project Feasibility: Precast facility confirmed feasible for projects within 300 km • Margin Guidance: Maintained at 11% to 13% • Dharoi Dam Project: Total development cost of Rs. 1,200 crore • Interest Costs: Expected to decrease as loans are repaid • Order Inflow Target for FY24: Confirmed over Rs. 3,000 crore
Conclusion • Call Closure: Management expressed confidence in future opportunities and encouraged further inquiries through Investor Relations.
PSP Projects Limited Q4FY23 Earnings Conference Call Summary
Date and Participants • Date: May 24, 2023 • Call Date: May 18, 2023 • Participants: • P.S. Patel (Chairman and CEO) • Hetal Patel (CFO) • Amar Kedia (Moderator, Ambit Capital)
Key Achievements in FY23 • Order Inflow: ₹3,421 crore (90% increase from FY22) • Outstanding Order Book: ₹5,052 crore • Recent Orders: ₹758 crore • Key Projects: High-rise buildings, airport development, management institute campus
Financial Performance • Revenue Growth: 10% for FY23; 31% year-on-year for Q4 FY23 • EBITDA and Net Profit: Decreased by 12% for Q4 and FY23 • Revenue Target for FY24: ₹2,600 crore • EBITDA Margin Guidance: 11%-13%
Project Updates • Uttar Pradesh Projects: Seven projects with completion dates extending into late 2023 and early 2024 • Precast Facility: Established to enhance project execution speed and quality • Total Projects Completed: 205 since inception in 2008
Financial Guidance and Challenges • Order Book Composition: 67% item rate contracts, 33% lump sum agreements • Working Capital Goals: Reduce debtor days from 41 to 30-35 days • Funding Needs: Securing an additional ₹450 crore
Future Opportunities • Bidding for Larger Projects: Including Central Vista (₹750 crore to ₹3,000 crore) • Infrastructure Sector Growth: Increased inquiries compared to previous years
Cash Flow and Losses • Cash Flow Decline: Due to increased receivables and inventory • Bhiwandi Project Losses: ₹9.5 crore booked; ongoing arbitration expected to resolve within a year
Additional Insights • Retention Money: Totaling ₹141 crore • Unbilled Revenue: ₹257 crore • Future Revenue Growth Potential: Discussion on reaching ₹4,000-5,000 crore, emphasizing execution capabilities and human resources
Conclusion • Call Closure: P.S. Patel thanked participants and encouraged further inquiries through investor relations.
PSP Projects Limited Q3FY23 Earnings Conference Call Summary
Date and Submission • Date of Call: January 18, 2023 • Submission to BSE and NSE: January 24, 2023 • Key Management Present: P. S. Patel (Chairman and CEO), Hetal Patel (CFO)
Financial Performance Highlights • Revenue Growth: • Q3 FY23 revenue from UP projects: Rs. 165 crores (39% QoQ growth) • Total revenue from operations: Rs. 497 crores (2% YoY increase) • EBITDA: • Decreased by 17% to Rs. 62 crores • EBITDA margin: 12.39% • Net Profit: • Fell by 25% to Rs. 35.32 crores • PAT margin: 7%
Order Book and Project Updates • Total Order Book: Rs. 5,075 crores • Recent Contracts: • Rs. 1,344.01 crore contract from Surat Municipal Corporation • Highest-ever order inflow: Rs. 1,950 crores in first nine months of FY23 • Ongoing Projects: 46 projects primarily in Gujarat, UP, and Maharashtra • Bid Pipeline: Approximately Rs. 4,500 crores, mainly from private projects
Future Projections • Revenue Targets: • FY23: Rs. 21 billion • FY24: Rs. 26-27 billion (20-25% growth expected) • Execution Expectations: • Q4 FY23 projected revenue: Rs. 900 crores • Surat Municipal project expected to generate Rs. 300-350 crores in first year
Financial Position • Cash and Bank Balance: Rs. 316 crores • Debt: • Long-term: Rs. 51 crores • Short-term: Rs. 140 crores • Increased Expenses: Higher employee expenses and finance costs due to staffing and project financing needs
Challenges and Concerns • Execution Delays: • Attributed to project approval delays in Uttar Pradesh • Competition: • Concerns about competition from larger EPC players
Additional Inquiries • Precast Revenue: • Rs. 60 crores booked from precast elements, with a backlog of Rs. 153 crores • Surat Municipal Project: • Land acquisition confirmed, project expected to start within 1-1.5 months, completion in 36 months
Conclusion • Management expressed optimism about future growth and thanked participants for their support.