Petronet LNG Limited Q1 FY25 Conference Call Summary
Financial Performance • Strong Metrics: • Dahej terminal throughput: 248 TBTU (13% increase QoQ, 14% YoY) • Overall terminal throughput: 262 TBTU (12% increase QoQ, 14% YoY) • Profit Figures: • Profit Before Tax (PBT): Rs. 1,520 crores (53% increase QoQ) • Profit After Tax (PAT): Rs. 1,142 crores (55% increase QoQ) • Contributing Factors: Higher throughput, stable LNG prices, operational efficiency.
Capital Expenditure (CAPEX) Updates • Project Progress: • Petrochemical project advancing with major contracts awarded. • Environmental clearances obtained. • CAPEX Distribution: • 20% in the first year, 30-40% in subsequent years. • Dahej terminal expansion expected completion by March 2025 (CAPEX: Rs. 570 crores). • FY2025 CAPEX Target: Approximately Rs. 3,500 crores.
Operational Insights • Dahej Terminal Utilization: Currently at 109%. • Inventory and Trading Margins: • Inventory gain: Rs. 261 crores. • Trading margin: Rs. 58 crores. • Future Expectations: Additional cargoes expected post-September.
Financial Clarifications • Expenses and Provisions: • Rs. 63 crores classified as other expenses due to revenue reversal. • Rs. 129 crores provision impacting financials. • Regas Service Income: Approximately Rs. 851 crores.
Q&A Highlights • Accounting Treatment: Clarifications on provisions and revenue reversals. • Take-or-Pay Contracts: Ongoing discussions with off-takers; shareholder interests protected. • Trade Receivables: Active pursuit of payments; bank guarantees can be encashed if obligations are unmet.
Future Prospects • LNG as Auto Fuel: Active SSLNG projects with four stations nearing commissioning. • Kochi Terminal Utilization: Currently 20%-25%, expected to rise to 50%-60% post-connection to National Gas Grid in March 2025.
Conclusion • The call concluded with appreciation for participants and management, emphasizing ongoing projects and future growth potential.
Petronet LNG Limited Conference Call Summary (May 23, 2024)
Financial Performance • Record Throughput: 234 TBTU for Q4, a 26% increase YoY. • Profit Before Tax (PBT): Rs. 996 crores for Q4; annual PBT of Rs. 4,757 crores (all-time high). • Profit After Tax (PAT): Rs. 738 crores for Q4; annual PAT of Rs. 3,536 crores (all-time high). • Dividend Declared: Final dividend of Rs. 3 per share.
Capacity Expansion Plans • Dahej Terminal: Expansion from 17.5 MMTPA to 22.5 MMTPA by March 2025. • New Gopalpur Terminal: Expected completion in three years; off-take arrangements still being finalized.
Market Demand and Pricing • LNG Demand: Current utilization at Dahej terminal is 97%; 20% YoY growth expected for FY25. • Competitive Pricing: LNG prices competitive with domestic gas prices.
Financial Metrics and Provisions • Regas Revenue: Rs. 674 crores reported. • IndAS Impact: Gross margin positive of Rs. 160 crores; various expenses detailed. • Provisioning for Charges: Based on a percentage of outstanding charges; specific amounts allocated for each year.
Petrochem Project and Future Plans • Greenfield LNG Terminal Cost: Estimated at Rs. 5,500 crores for 5 MMTPA capacity. • Petrochem Project: Financial commitment made; off-take arrangements with Qatar Energy to be negotiated.
Competition and Market Position • Competition Concerns: New terminals like Chhara and Dabhol discussed; Dahej's superior connectivity emphasized. • Inventory Losses: Rs. 107 crores from non-committed inventory.
Cash Management and Future Outlook • Cash Balance: Approximately Rs. 9,000 crores; average cash closer to Rs. 7,000 crores. • CAPEX Plans: Aggressive spending planned for FY25 and FY26; ongoing projects include Dahej expansion.
Additional Insights • Kochi-Bangalore Pipeline: Completion expected by March 2025; will enhance utilization levels. • Use-or-Pay Receivables: Provisions made; confidence in recovering amounts highlighted. • Gopalpur Terminal Potential: Economic advantages due to pipeline proximity; confidence in future performance expressed.
Conclusion • Growth Trajectory: Encouragement to trust in the company's growth despite competition; positive outlook on performance.
Petronet LNG Limited Conference Call Summary (January 30, 2024)
Financial Results • Record Profits: • Profit Before Tax (PBT): INR 1,597 crores • Profit After Tax (PAT): INR 1,191 crores (46% increase from previous quarter) • Throughput Growth: • Total throughput for Dahej and Kochi terminals: 232 TBTU (21% increase over nine months)
Management Insights • Operational Efficiency: Growth attributed to high utilization of the Dahej terminal. • LNG Trade Concerns: Long-term contracts with QatarEnergy unaffected by Red Sea disruptions. • Receivables Update: Ongoing efforts to collect outstanding amounts.
Receivables Discussion • Use or Pay Charges: • Totaling INR 1,263 crores for 2021 and 2022. • Settlement reached allowing three-year compensation via bank guarantees. • Provisions: • INR 228 crore provision created against receivables, to be reversed upon delivery.
Capital Expenditures and Projects • Dahej Terminal Expansion: On track for completion by March 2025. • Petrochemical Project: Approved with an investment of INR 20,685 crores, currently in licensor selection phase. • Kochi Pipeline Connectivity: 250-kilometer section expected completion by year-end.
Additional Financial Insights • Inventory Gains: Reported at INR 147 crores. • Regasification Charges: Increased by 5%, contracts honored until 2036 for 8.25 MMTPA. • Bank Guarantees: • Outstanding amounts: INR 415 crores (2021) and INR 848 crores (2022). • Some guarantees received, others in process.
Future Strategy • New Terminal at Gopalpur: Gangavaram project abandoned; expected completion in three years. • Dahej Jetty Project: Budget of INR 1,700 crores, 36-month completion timeline. • Volume Strategy for 2026: No additional efforts to increase volumes, but flexibility in resource direction maintained.
Conclusion • Commitment to Growth: Ongoing focus on enhancing profitability and shareholder value. • Gratitude: Management expressed thanks to participants at the call.
Petronet LNG Limited Analyst/Investor Meet Summary
Meeting Overview • Date & Time: November 3, 2023, from 4:00 PM to 6:00 PM IST • Attendees: Key management members including MD & CEO Shri A.K. Singh and Director Finance Shri V.K. Mishra • Purpose: Provide updates on company initiatives; information shared was not price-sensitive.
Company Operations • Core Business: LNG sourcing and regasification. • Terminals: Operates two terminals - Dahej (world's busiest, full capacity) and Kochi. • Dividends: Consistent payment for 17 years; recently achieved a five-star safety rating.
New Petrochemical Project • Investment: Rs. 20,685 crores in a petrochemical project at Dahej. • Production: Focus on propylene and polypropylene; project completion expected in four years. • Integration: Utilizes cold energy from LNG; proximity to feedstock and consumers emphasized.
Market Demand and Financial Viability • Demand for Polypropylene and Ethane: Confidence in meeting market needs; strong credit ratings indicate financial viability. • Sourcing: Ethane primarily from the U.S.; propane from the Middle East and U.S. • Capacity Utilization: Historical data used for projections; project completion by October 2027.
Project Structure and Economics • Project Structure: Confirmed as part of Petronet, not a separate SPV. • Unit Economics: Propane to propylene conversion rate around 85%; project meets equity IRR benchmark above 16%. • Revenue Streams: Additional revenue from ethane and propane handling through a tolling model.
Dividend Concerns • Dividend Reduction: 15% reduction clarified; commitment to maintaining and potentially increasing dividends. • Cash Reserves: Company has substantial cash reserves (₹7,800 crores) to fund projects.
Risk Management and Strategic Positioning • Risk Mitigation: One-third of project product has guaranteed off-take; unique handling and storage model. • Market Positioning: Strategic advantages of Dahej location; thorough risk assessments in place.
Closing Remarks • Acknowledgments: Concluded with thanks to participants and management for their contributions.
Petronet LNG Limited Q2 FY24 Earnings Conference Call Summary
Key Financial Highlights • Total Throughput: 223 TBTU for Q2, slight decrease from previous quarter, 16% increase year-over-year. • Profit Before Tax (PBT): ₹1,102 crores. • Profit After Tax (PAT): ₹818 crores, significant growth compared to previous periods. • Interim Dividend: ₹7 per share, consistent payout ratio.
Major Project Announcements • Petrochemical PDH/PP Project: • Approved investment of ₹20,685 crores. • Expected project IRR: 20%, equity IRR: 30%. • Aims to enhance profitability and mitigate risks through long-term agreements. • Ethane Handling System: Planned to operate on a tolling model to reduce risk exposure.
Q&A Session Insights • IRR Projections: Based on a seven-year average of propane and propylene prices, excluding 2021. • Project Cost Increase: From ₹14,000 crores to ₹20,000 crores due to ethane handling facility and soft costs. • OPEX and EBITDA Estimates: Initial profit generation of ₹2,000 crores, growing to ₹7,000 crores at full capacity by 2027-2028.
Future Plans and Updates • Gopalpur Project: Documentation being finalized. • Dahej Terminal Expansion: On track for completion by March 2025, CAPEX of ₹570 crores. • Regasification Tariffs: Confirmed rates of ₹59.91 per MMBTU for Dahej and ₹85.09 for Kochi.
Market Outlook • Polypropylene Demand: Projected increase over the next 5-10 years despite current supply shortfalls. • LNG Supply Security: India has secured around 20 million tons of LNG contracts, emphasizing long-term agreements.
Additional Notes • Third Jetty at Dahej: Approved with a CAPEX of ₹1,645-1,656 crores, separate from main project costs. • Future LNG Supply: Significant increase expected by 2027, particularly from Qatar. • Management's Optimism: Expressed confidence in future growth and thanked participants, wishing them a happy Diwali.
Petronet LNG Limited Q1 FY 2024 Conference Call Summary
Key Highlights • Throughput Growth • Dahej Terminal processed 217 TBTU, a 26% increase from the previous quarter. • Overall utilization across both terminals reached 230 TBTU, up 24%.
• Financial Performance • Profit Before Tax (PBT): INR 1,062 crores (record high). • Profit After Tax (PAT): INR 790 crores (record high).
Competition and Contracts • Concerns Addressed • Potential competition from GAIL's Dabhol facility mitigated by long-term contracts.
• Long-term Contracts • Regasification contracts extend until 2036, totaling 8.25 MMTPA with major clients.
Project Updates • Petrochemical Expansion • Preliminary activities ongoing; further developments expected in the coming months.
• East Coast Terminal • Commitment to FSRU proposal; potential shift to land-based terminal due to market conditions.
Financial Insights • Regasification Margins • Gross contribution: INR 717 crores. • Average regasification tariffs: INR 59 (Dahej), INR 85 (Kochi).
• Outstanding Payments • Total outstanding payments from contracted year 2022: INR 843 crores.
Market Conditions • LNG Pricing • Current prices around USD 10-11; stability expected in the near term.
• European Market • Stable prices due to sufficient inventory levels.
Future Outlook • Capacity Expansion • Ongoing discussions with potential off-takers for new LNG purchase contracts.
• Dividend Policy • Commitment to maintain a dividend of at least 100% of paid-up capital.
• Growth Prospects • Optimism for growth in biogas and LNG segments despite previous delays.
Conclusion • Positive performance in Q1 FY 2024 with expectations for continued improvement and commitment to enhancing profitability and shareholder trust.
Petronet LNG Limited Conference Call Summary (May 3, 2023)
Financial Results • Revenue: ₹59,899 crores (39% increase YoY) • Profitability: • Profit Before Tax (PBT): ₹4,335 crores (decline) • Profit After Tax (PAT): ₹3,240 crores (decline) • Dividends: ₹3 per share announced
Operational Performance • Throughput: • Dahej terminal: 704 TBTU (decrease) • Kochi terminal: Decreased throughput • Factors Affecting Profitability: Foreign exchange variations
Key Projects and Capital Expenditure • Dahej Expansion: • Total capex: ₹1,650 crores (₹744 crores spent) • Capacity increase from 17.5 to 22.5 MMTPA • Future Projects: • Kochi tank: ₹600 crores • Gopalpur FSRU terminal: ₹2,300 crores • FY2023-2024 Capex Outlook: Estimated at ₹1,700 crores
Management Insights • Dividend Payouts: Aiming for a 100% payout ratio • Receivables: Ongoing recovery efforts for ₹850 crores owed • FSRU Construction Challenges: Global supply chain issues; alternative land-based terminal plans discussed
LNG Utilization and Pricing • Utilization Rates: • April: Increased to 97% from 77% • Kochi: Currently at 20%, potential increase with new pipeline • Trading Margins: Spot LNG sales at ₹73 crores for the quarter
Future Outlook • ExxonMobil Volumes: Expected increase to 1.2 MMTPA by 2028 • Biogas and LNG Stations: Plans for compressed biogas stations and ongoing LNG installations • RasGas Contract: Renewal expected by end of 2023
Financial Metrics • Trading Gains: ₹73 crores reported • Forex Impact: Positive gain of ₹23 crores • Capex for FY2023: Confirmed at ₹950 crores
Market Position • Long-term Contracts: 15.75 MMTPA booked at Dahej, securing capacity against new terminals • Profit Growth Outlook: Optimism for FY2024 based on capacity utilization and gas prices
Conclusion • Business Model: Management reassured of Petronet LNG's robustness and profitability assurances.
Petronet LNG Limited Conference Call Summary (January 20, 2023)
Financial Results • Record Figures for Nine Months (Ending December 31, 2022) • Turnover: INR 46,025 crores • Profit Before Tax (PBT): INR 3,517 crores • Profit After Tax (PAT): INR 2,626 crores • Growth: 44% increase in turnover compared to the previous year • Q3 Results • PBT: INR 1,586 crores • PAT: INR 1,118 crores
Operational Highlights • Terminal Processing • Dahej Terminal: 154 TBTU • Kochi Terminal: 13 TBTU • Outstanding Payments • Total outstanding: INR 849 crores
Long-term Contracts and Receivables • Long-term Volumes • No issues with contracts (Rasgas, ExxonMobil) • Service volumes below expectations • Receivables and Cash • Total receivables: INR 3,513 crores (INR 1,200 crores from long-term contracts) • Net cash: INR 6,900 crores
Capital Expenditure Plans • Current Projects • Two tanks under construction (50% progress) • New jetty project in tendering phase • Future Investments • Terminal at Gopalpur and PDH-PP plant in Dahej
Service Income and LNG Prices • Service Income • Reported at INR 1,112 crores for the current quarter • LNG Price Impact • Management hopeful for increased regasification volumes if prices remain low
Financial Outlook • FY 24 Expectations • Anticipated breakeven • Utilization Levels • Increased to 81% from 68% in the previous quarter
Volume Predictions and Dividends • Fourth Quarter Predictions • Management reassured no cash shortage affecting dividends • Receivables Management • Actively pursuing outstanding receivables
Long-term LNG Sourcing • Contract Renewals • Negotiating for reasonably priced gas to avoid high long-term costs
Regasification Charges • Current Charges • Dahej: INR 59.91 • Kochi: INR 81.04 • Pending Amounts • INR 4.2 billion related to take-or-pay contracts
Future Capacity and Projects • Capacity Utilization • Projected over 80% for the upcoming year • Dahej Expansion • Expected addition of 5 MMTPA by March 2025 • Petrochemical Project • Planned capex of INR 13,000 crores with an equity IRR target of over 16%
Conclusion • Management Commitment • Focus on increasing profitability despite high LNG prices and challenging macro environment.