Mazagon Dock Shipbuilders Limited Q4 FY24 Earnings Call Summary
Key Highlights • Record Performance: Surpassed $1 billion in revenue; celebrated 251st Foundation Day. • Liquidated Damages: Confirmed write-back of INR 141 crores in Q4; pending refunds of INR 300 crores for two submarines.
Project Updates • Ongoing Projects: Updates on P-75 add-on submarines and 75I project with expected completion timelines. • Upcoming Deliveries: First of 17A frigates targeted for FY’25; potential delivery of two frigates within the year.
Financial Projections • Revenue Expectations: FY’25 revenue projected at INR 10,000 to 10,500 crores; margins expected to remain stable or improve. • Order Book Growth: Anticipated increase to INR 40,000 to 50,000 crores depending on additional orders.
Capital Expenditures and Investments • Cash Allocation: INR 15,000 crores earmarked for projects; INR 4,000 crores considered free cash. • Investment Plans: INR 3,000 crores planned for capacity expansion over the next 3-4 years.
Warranty and Spare Parts Discussion • Warranty Costs: Difficult to quantify due to variability; spares account for around 13% of large orders. • Capex Plans: Expansion at two facilities to enhance shipbuilding and repair capabilities.
Order Book and Execution • Total Order Book: Approximately INR 38,000 crores, including destroyers, frigates, submarines, and coast guard vessels. • Pending Orders: Frigates pending around INR 17,000 crores; additional amounts for submarines and export orders.
Conclusion • Navy Procurement Plans: Management not privy to certain internal Navy documents; confirmed liquidated damages of INR 300 crores for FY '24. • Margin Improvements: Current contracts affect margin predictability; funds for projects are made available as needed.
Mazagon Dock Shipbuilders Limited Q3 FY24 Earnings Conference Call Summary
Key Highlights • Record Profits: Achieved highest-ever quarterly and nine-month profits. • Timely Deliveries: Success attributed to timely submarine deliveries and favorable resolutions on liquidated damages from the Indian Navy.
Project Updates • Submarine Projects: • Status of three add-on submarines and P-75I AIP program. • Contract awards expected within 4 to 8 months. • Destroyers and Frigates: • Delivered third destroyer, Imphal, in October 2023. • Fourth destroyer planned for FY25 (Q2/Q3). • First of the 17A frigates expected before December 2024.
Financial Overview • Cash Balance: Over ₹3,000 crores as of December 31, excluding advances. • Liquidated Damages: Received approximately ₹160 crores in Q3; similar expected for Q4. • Order Book: Stood at ₹38,389 crores, with plans for liquidation through ongoing deliveries.
Future Orders and Market Outlook • New Orders: Over ₹7,000 crores booked for FY24, including contracts from Coast Guard and ONGC. • Market Exploration: Optimism about exploring new markets, though current naval budget allocations may limit order materialization.
Profitability Insights • Margin Variability: Profitability influenced by contract type and project experience. • Contract Liabilities: Manageable liabilities around ₹9,000 to ₹10,000 crores, balanced by work in progress.
Strategic Developments • Aircraft Carrier Projects: Not pursuing due to low demand. • Submarine Projects: Ongoing work on additional Scorpène submarines and P-75I project. • Infrastructure Plans: • Development of 37-acre land in Nhava Sheva and Floating Dry Docks project. • Floating Dry Dock project estimated at ₹500 crores over 2.5 years.
Export Potential • Southeast Asia: Efforts to export naval vessels complicated by varying defense budgets and requirements.
Conclusion • Investor Interaction: Sanjeev Singhal expressed appreciation for investor engagement during the call.