Bansal Wire Industries Limited Q1 FY 2025 Conference Call Summary

Financial PerformanceNet Profit: Increased by 82% to Rs. 31 crores • Revenue: Up 49% to Rs. 817 crores • EBITDA: Rose 127% to Rs. 62 crores • EBITDA Margin: Improved by 260 basis points to 7.6%

Company PositionMarket Standing: Second-largest steel wire producer in India; largest stainless steel wire producer • Manufacturing Facilities: Five facilities with a diverse customer base • Sales Volume: 140% year-over-year increase, totaling approximately 76,000 tonnes

Future PlansSpecialty Wires: New vertical planned for Q3 2024, facing delays due to supply chain issues • Production Timeline: • Specialty wire production expected to start by November/December 2023 • Hose wire sales anticipated soon after • Bead wire production expected by end of current quarter or early next quarter

Growth ProjectionsHistorical Growth Rate: 20-25% • EBITDA Increase: Projected 80% for the current year • Revenue Target: Rs. 2,000 crores from steel cord in 5-6 years with a 25% EBITDA margin • Return on Capital Employed (ROCE): Improved from 18.46% to 23.85%

Production and Market StrategySteel Cord Production: Aiming to be the first Indian manufacturer, with plans to produce hose wire initially • Market Size: Approximately 250,000 tonnes for steel cord, with plans to scale to 200,000 tonnes • Specialty Wires: Plans to produce IHT and OHT wires for electric vehicles

Capital Expenditures (CAPEX)Dadri Plant: Total CAPEX of Rs. 500 crores, with Rs. 250 crores already spent • New Steel Wire Facility: Rs. 150 crores invested for 20,000 tonnes capacity • Larger Facility: Projected CAPEX of Rs. 2,500 crores over five years

Operational InsightsNet Cash Generation: Negative Rs. 41 crores in Q1 due to investments • Working Capital Cycle: 70 days • Utilization Rates: Manufacturing facilities operating at 88-90% • Peak Revenue Potential: Anticipated at Rs. 5,000 crores once Dadri facility is operational

Debt and Financial ManagementGross and Net Debt: Rs. 816 crores and Rs. 813 crores, respectively • Production Margins: Hose wire margin projected at Rs. 80-90 per kg • Consolidation: Shutting down two group companies to streamline operations

Production Capacity GoalsCurrent Production Mix: • 27,000 tonnes of high carbon • 28,000 tonnes of mild steel • 21,000 tonnes of stainless steel • Capacity Expansion: Aiming to increase annual capacity from 2.5 lakh tonnes to 6 lakh tonnes by year-end